RLW was the concrete subcontractor for a major replacement/modernization of the City Creek Water Treatment Plant, designed to handle 16 MGD of water. Early work included VDC/BIM modeling, shoring, and the installation of soil nail walls to expand the work areas for the entire project team. In total, crews placed 7,000 cubic yds. of concrete to build the structures at the site, which included two flocculation and sedimentation basins, six filters, and a clearwell/backwash tank.